First Group – Essex Thamside
Overview
Part of a large rail franchise bid, OHC were commissioned to produce the hard services submission, comprising strategy, condition survey, bid writing, maintenance and life cycle costing.
Due the life cycle responsibilities under the FRI lease terms of the contract, OHC undertook a detailed survey of all the assets to inform the asset replacement programme. These assets were reviewed against their condition status and assessed life expectancy. Once this was established, a full cost modelling exercise for a 15 year period was undertaken against Network Rail’s Percentage Asset Remaining Life (PARL) methodology to calculate the potential cost impact against this rigorous standard.
“Terrific response from Oxhey Hall. Great all-round capability and innovative approach.”
OHC’s strength and depth allowed us to undertake all these services in-house to produce a comprehensive and cohesive submission.
- Number of Assets: 3,000 100%
- Gross Internal Area: 12,000 m2 100%
- Programme: 10 Days 100%
Client
First Group
Establishments
29 Railway Stations. Essex Thameside
Service
Asset Verification and Condition Survey with Labour Loading and Life Cycle Costing. M&E and Fabric
Capture
Manual capture and desktop costings